In California Water Impact Network v. County of San Luis Obispo (2018) 25 Cal. App. 5th 666, the Second District Court of Appeal held that the approval of groundwater well permits was a ministerial act and not subject to CEQA environmental review because no discretion was exercised when such permits were issued.

County of San

In LandWatch San Luis Obispo County v. Cambria Community Services District (2018) 25 Cal.App.5th 638, the Second District Court of Appeals affirmed an agency may properly take over the preparation of the administrative record per Public Resources Code section 21167.6(b)(1) when petitioner elects to prepare and fails to do so within 60 days.

LandWatch San

In World Business Academy v. California State Lands Commission (2018) 24 Cal.App.5th 476, the Second Appellate District determined that renewing a lease for an existing power plant constituted a categorically exempt “existing structure” project under CEQA and the record did not support an “unusual circumstances” exception to the exemption.

Diablo Canyon Power Plant is a

In County of Ventura v. City of Moorpark (2018) 24 Cal.App.5th 377, the Second Appellate District upheld a CEQA statutory exemption applied to a project undertaken by the State-created Broad Beach Geologic Hazard Abatement District (BBGHAD) and clarified that a “project” for CEQA consideration may be two separate activities if they serve a single purpose,

The CEQA Statute and Guidelines both contain provisions outlining what types of projects are exempt from environmental review. There are dozens of exemptions, however, that are listed in other provisions of the California codes that can be difficult to find. On June 6, 2018, the Governor’s Office of Planning and Research (OPR) released a helpful

In a March 2018 decision, the First Appellate District examined several CEQA issues pertinent to petroleum refining and hazardous materials transport.  In Rodeo Citizens Association v. County of Contra Costa, the appeals court affirmed several findings of the lower court, dismissing challenges to the environmental impact report (“EIR”) prepared for a propane and butane recovery project at the Phillips 66 refinery in Rodeo.  (The appeals court did not review the trial court’s order to the county to set aside the certification of the EIR and correct several other air quality related issues.)  The appeals court found the risk of rail transportation of propane and butane was appropriately measured against the baseline of existing risks; the project description did not mask plans for the refinery to alter its crude oil feedstock; and that greenhouse gas impacts from downstream uses of petroleum products need not be evaluated.

In La Mirada Neighborhood Association v. City of Los Angeles (2018) 22 Cal.App.5th 1149, the Second District Court of Appeal held that attorneys’ fees were properly awarded per California Code of Civil Procedure section 1021.5 (Section 1021.5) where the challengers were successful in conferring a significant benefit in the public interest—invalidating six of eight specific

The United States Supreme Court will not be taking up the California Supreme Court’s July 2017 decision in the Friends of the Eel River case.  In that decision, authored by Chief Justice Cantil-Sakauye, the California Supreme Court held that the federal Interstate Commerce Commission Termination Act (ICCTA) did not preempt application of CEQA to the

In Jensen v. City of Santa Rosa (2018) 23 Cal.App.5th 877, the First Appellate District held that noise impacts from a proposed youth center and transitional housing project were properly analyzed and approved with a negative declaration (ND) where the City of Santa Rosa’s (City) acoustic expert found no noise impacts above the baseline would

On January 12, 2018, the First Appellate District held that the California Attorney General need not exhaust administrative remedies in order to contest the adequacy of Environmental Impact Reports (EIRs) under the California Environmental Quality Act (CEQA), as is normally required of third-party challengers under Section 21177.  City of Long Beach v. City of Los Angeles, Case No. A148993 (2018).  The Appeals Court also held that BNSF Railway Company’s (BNSF) proposed construction of a new railyard in Southern California failed to adequately consider air quality impacts from the project.  The case emphasizes the need for EIRs to consider impacts to ambient air pollutant concentrations and the cumulative impacts of such pollutants under CEQA, even if the underlying analysis may be time consuming and difficult to generate.