Biden’s Inauguration Day Executive Order on Environment and Energy Regulation

On his first day in office on January 20, 2021, President Biden signed an Executive Order titled, “Protecting Public Health and the Environment and Restoring Science to Tackle the Climate Crisis” (the Order). The Order directed federal agencies to immediately begin a review of federal regulations and regulatory action over the last four years. The Order directed agency heads to consider revision, rescission, or suspension of regulations rather than directing any particular course of action. However, the Order illuminates the Biden Administration’s priorities with respect to the regulatory landscape for energy and the environment. Continue Reading

Judge Suspends State Procedures as Applied to Majority of Waters of the State; Retains Application to Waters Subject to the Clean Water Act and All Ocean Waters Regardless of Jurisdiction

On December 17, 2020, the Sacramento County Superior Court substantially limited the scope of waters to which the State Procedures for Discharges of Dredged and Fill Material (“Procedures”) apply through its decision in San Joaquin Tributaries Authority v. State Water Resources Control Board (Case No. 34-2019-80003133).  According to the Court, the State Water Resources Control Board (“State Water Board”) exceeded its policy-making and water quality control plan development authority, resulting in the restriction of the Procedures to those waters regulated under the Federal Water Pollution Control Act or Clean Water Act (“CWA”) and State “ocean waters.”  The Court’s decision significantly narrows the delta between the discharges of dredged and fill material regulated exclusively under the Procedures, and those that will now be regulated under both federal and state water quality control laws.  However, because the Court’s opinion did not invalidate the Procedures in their entirety, permittees will still need to evaluate application of the Procedures, though to a constricted set of waters and aquatic features. Continue Reading

First Appellate District Approves Responsible Agency’s Imposition of Mitigation Not Considered in the EIR

In an opinion filed on December 29, 2020, the First Appellate District in Santa Clara Valley Water District v. San Francisco Bay Regional Water Quality Control Board upheld a Responsible Agency’s imposition of additional mitigation more than a year after it had issued an initial approval for the project.  Although the court was careful to say that it was addressing “unique circumstances” that would “seldom arise,” the decision is potentially problematic for project proponents, and especially for public agencies trying to pursue necessary public-infrastructure projects. Continue Reading

In Martis Camp Ruling, Subsequent Review Under CEQA Hinges on the Right EIR

In an opinion published on August 17, 2020, the Third Appellate District in Martis Camp Community Association v. County of Placer ruled that Placer County had violated CEQA by adopting an addendum to support abandonment of a roadway. Despite the statutory presumption against subsequent review under CEQA, the Third District determined that the County had abused its discretion in relying on the wrong EIR as a basis for analysis. Continue Reading

California Supreme Court Throws the Barn Doors Open, Finding That Groundwater Well Permits Aren’t Necessarily Ministerial

On August 27, 2020, in Protecting Our Water and Environmental Resources v. County of Stanislaus, Case No. S251709 (“Protecting Our Water”), the California Supreme Court held that the County in that instance could not categorically classify its issuance of groundwater well construction permits as ministerial decisions exempt from environmental review under the California Environmental Quality Act (“CEQA”) (Pub. Resources Code, §§ 21000 et seq.).  While the Court’s Opinion does not state that all well permits must undergo CEQA review, it narrows the grounds on which the ministerial exemption may apply.  And since county well ordinances across the State comprise similar provisions, this ruling upsets the common practice of treating such permits as ministerial, not subject to CEQA.  More importantly, however, the Court’s ruling interrupts a growing trend in the cases to provide some relief from CEQA where agencies lack sufficient discretion, and creates uncertainty for lead agencies by holding that ministerial permitting decisions must be reviewed on a case-by-case basis. Continue Reading

Agency Email Correspondence Must be Retained Under CEQA, Appeals Court Holds

In a ruling that should send shivers up the spine of any public agency in California needing to comply with the California Environmental Quality Act (“CEQA”), the Fourth District Court of Appeal on July 30 held that any email correspondence related to a project and its compliance with CEQA must be retained as part of the agency’s record of administrative proceedings, even if the agency’s document retention policy states otherwise.  This marks the first ruling (or statute or regulation) to impose such a duty.

Golden Door Properties, LLC v. Superior Court of San Diego, Lead Case No. D076605, stems from numerous CEQA writ petitions related to San Diego County’s (“County”) approval of the Newland Sierra Project.  The specific issue in the opinion is the impact of the County’s document retention policy, which directed City staff to automatically delete emails not marked or saved as “official records” after 60 days.  In some tension with that retention policy, Public Resources Code sub-sections 21167.6(e)(7) and (e)(10) require agencies to include external and non-privileged internal emails and other written communications related to a CEQA project in the administrative record of proceedings when litigation is filed challenging the project under CEQA.  In this instance, the County argued that some emails related to the project and its compliance with CEQA had been deleted pursuant to the County’s document retention policy and thus could not be produced in response to discovery or for the administrative record.  A battle over discovery of the records ensued.  Ultimately, a trial court discovery referee ruled that there was no duty to retain emails under CEQA, and therefore denied efforts by petitioners to compel the agency to produce the records. Continue Reading

Sixth District Holds CEQA Does Not Require Supplemental Review for a Streambed Alteration Permit

Willow Glen Trestle Bridge (Photo by Don DeBold, via Flickr)

The Sixth Appellate District, in Willow Glen Trestle Conservancy v. San Jose (2020) 49 Cal.App.5th 127, held that seeking a new Streambed Alteration Agreement (“SAA”) from the California Department of Fish & Wildlife (“CDFW”) for a previously approved project does not constitute a “further discretionary approval” within the meaning of CEQA Guidelines section 15162 and therefore does not require supplemental review.

In 2014, the City of San Jose approved a project to demolish the Willow Glen Railroad Trestle, a railroad bridge over Los Gatos Creek, and replace it with a new steel truss pedestrian bridge. The City approved the project with a Mitigated Negative Declaration (“MND”). The original SAA approved in conjunction with the MND expired. Subsequently, the City applied for, and was granted, an SAA from CDFW to divert the creek during demolition and construction of the new bridge. The Willow Glen Trestle Conservancy challenged the City’s approval of the SAA, arguing that the SAA required subsequent CEQA review. The trial court determined the 2018 SAA did not involve further discretionary approval and petitioners appealed.

Petitioners challenged the 2018 SAA arguing that the new application amounted to a “discretionary approval,” triggering mandatory supplemental review under Public Resources Code section 21166.  Section 21166 and its counterpart CEQA Guideline 15162 compel subsequent review in limited circumstances when, after the original approval of a project, a “further discretionary approval on that project” is required. The petitioners argued that the City’s act of seeking and accepting the SAA was a discretionary approval by the City. The court held that while CDFW’s issuance of the final SAA was a CDFW approval, that action did not amount to a City approval. However, the petitioners had failed to challenge CDFW’s approval of the SAA.

Relying on the subsequent review principles articulated by the California Supreme Court in Friends of College of San Mateo Gardens v. San Mateo Community College District (2016) 1 Cal.5th 937, the court emphasized that Section 21166 and CEQA Guidelines section 15162 are intended to limit the circumstances under which subsequent review is required by stating that information appearing after an approval does not require reopening of that approval. These limitations are meant to “balance CEQA’s central purpose of promoting consideration of the environmental consequences of public decisions with interests in finality and efficiency.” (Friends of College of San Mateo Gardens v. San Mateo Community College District (2016) 1 Cal.5th 937, italics added.) If every action taken to implement an approved project was considered another approval of the project, the City’s final consideration of the project would be subject to endless reopening.

The court concluded that the City’s 2018 SAA application was a step in implementing the already approved project, not a further discretionary approval, because obtaining a SAA was contemplated in the MND. Consequently, the City was not required to conduct supplemental review for the 2018 SAA.

Trump Signs Executive Order Allowing Agencies to Bypass NEPA, ESA, and CWA Requirements

On June 4, 2020 President Trump signed an Executive Order titled “Accelerating the Nation’s Economic Recovery from the COVID-19 Emergency by Expediting Infrastructure Investments and Other Activities,” allowing—and, in fact, directing—federal agencies to circumvent environmental permitting requirements in order to expedite infrastructure projects. The Order is based on the President’s March 13, 2020 declaration of national emergency due to the Novel Coronavirus Disease (“COVID-19”) outbreak and the resulting dramatic downturn in the economy; apparently, the administration concluded that “without intervention, the United States faces the likelihood of a potentially protracted economic recovery with persistent high unemployment.”

The Order directs federal agencies to take all reasonable measures to speed infrastructure investments in order to strengthen the economy. It focuses on expediting the delivery of transportation infrastructure projects, civil works projects, and projects on federal land, directing the Secretaries of Transportation, the Army, Defense, the Interior, and Agriculture to “use all relevant emergency and other authorities to expedite work on, and completion of, all authorized and appropriated” highway and other infrastructure projects; civil works projects; and infrastructure, energy, environmental, and natural resources projects on Federal lands that are within the authority of each of the Secretaries to perform or to advance. Continue Reading

COVID-19 Alert: Judicial Council Amends Emergency Rule 9 for CEQA and Planning Cases

On May 29, 2020, the Judicial Council of California issued a Circulating Order to amend its earlier-issued Emergency Rule 9 in order to shorten the time for tolling statutes of limitations for all civil causes and provide a fixed date, including for causes of action arising under the California Environmental Quality Act (CEQA) and State planning and zoning laws.   Under the amended Emergency Rule 9, the tolling period for civil actions with limitations periods that are less than 180 days—which includes most CEQA and planning and zoning law claims—expires on August 3, 2020.  This clarifies and dramatically reduces the time within which complaining parties must file civil litigation to challenge most CEQA and related land use approvals.

As we noted earlier, on April 6, 2020, the Judicial Council of California issued Emergency Rules to address impacts of the COVID-19 pandemic on the judicial branch.  This included Emergency Rule 9, which tolled the time to file any type of civil litigation from April 6, 2020, to until 90 days after the Governor lifts the state of emergency for the COVID-19 pandemic.  This created enormous uncertainty related to land use matters and CEQA actions, as the time to file such challenges is unusually short (30 to 90 days) and it is entirely unclear when the Governor might lift the state of emergency.  Emergency Rule 9 threatened to extend the limitations periods for CEQA and land use claims by months. Continue Reading

Second Appellate District Expands Baseline Analysis in Upholding Environmental Impact Report for Refinery Project Intended to Help Reduce Air Pollutants

Last month, the Second Appellate District upheld the South Coast Air Quality Management District’s (“Air District”) Environmental Impact Report (“EIR”), which the Air District prepared to analyze the environmental impacts of a refinery project that was intended to increase compliance and help reduce air pollution.  Communities for a Better Environment v. So. Coast Air Quality Mgmt. Dist., Case No. B294732 (Apr. 7, 2020).  The project applicant owns and operates two adjacent oil refining facilities in Southern California, and sought to improve the integration of both facilities to allow flexibility in product outputs, which also increased the refinery’s compliance with air regulations, and thus helped reduce air pollutants.  As explained in greater detail below, the decision is particularly noteworthy because the court appears to have expanded the “baseline” analysis tied to air emissions, which is used to measure pre-project vs. post-project impacts to the existing environment.

The Air District’s review of the underlying project took three years and the Air District’s Draft EIR was the subject of over 2,000 public comments, which included comments totaling 1,112 pages from the plaintiff that later challenged the project.  Significantly, 1,798 comments or 85% supported the project—likely because the EIR found that the main environmental impact of the project would be to reduce air pollution; and the Air District’s Final EIR was lengthy and robust, containing 6,075 pages of public comments alone. Continue Reading

LexBlog