In the unpublished Elfin Forest Harmony Grove Town Council v. County of San Diego (Oct. 14, 2021, Nos. D077611, D078101) [2021 Cal. App. Unpub. LEXIS 6474], the Fourth District Court of Appeal found that the County of San Diego’s (County) approval of the Harmony Grove Village project’s (Project) environmental impact report (EIR) did not employ

On August 19, 2021, in Save Our Access – San Gabriel Mountains vs. Watershed Conservation Authority, the Second District Court of Appeal, in reversing the lower court’s judgement, upheld an Environmental Impact Report’s (EIR’s) finding of less than significant impact under CEQA for an intentional reduction in parking meant to protect and restore the

In June 2021, the Third District Court of Appeal upheld the County of El Dorado’s (“County”) mitigated negative declaration (“MND”) for a bridge construction project against complaints that the project’s construction would block an evacuation route for residents in the event of a wildfire. In its holding in Newtown Preservation Society v. County of El

In Stop Syar Expansion v. County of Napa (2021) 63 Cal.App.5th 444, the First District Court of Appeal upheld Napa County’s Environmental Impact Report (EIR) for the expansion of Syar Industries, Inc.’s aggregate mining operations at a local quarry. Citizen group Stop Syar Expansion (“SSE”) filed a Petition for Writ of Mandate under CEQA claiming that the EIR was deficient on 16 counts, including in its analysis of greenhouse gas emissions, water usage baseline, water quality, and general plan consistency. The trial court denied the Petition for Writ of Mandate, and SSE appealed, raising five issues. The Court of Appeal affirmed, holding that SSE did not exhaust administrative remedies because it failed to raise specific issues in the administrative proceedings as required by the Napa County Code. Additionally, the Court denied SSE’s general plan consistency claim under CEQA, holding that general plan consistency is properly reviewed with traditional mandamus under Code of Civil Procedure section 1085.

In Carmel Valley Ass’n v. County of Monterey (2021) 2021 Cal.App.Unpub. LEXIS 3286, the Sixth District Court of Appeal reversed a decision granting a petition of mandate against the County of Monterey’s (County) approval of an environmentally superior alternative to a proposed mixed-use residential subdivision project (Project). The decision was issued on May 19, 2021, so any request for publication under Cal. Rules of Court 8.1120 is due by June 8, 2021.

In California Coastkeeper v. State Lands Commission, the Third District Court of Appeal upheld the State Lands Commission’s decision to prepare a supplemental environmental impact report (EIR) for a desalination plant in Huntington Beach, overturning an earlier trial court ruling that invalidated the EIR.  Limited changes to a desalination project were proposed in order

On December 11, 2019, the California Supreme Court granted review of the Third District’s decision in County of Butte v. Department of Water Resources, dismissing a CEQA challenge to DWR’s relicensing application to the Federal Energy Regulatory Commission (FERC) for the Oroville Dam on the basis that the claim was preempted by federal law. The

In an opinion filed on December 29, 2020, the First Appellate District in Santa Clara Valley Water District v. San Francisco Bay Regional Water Quality Control Board upheld a Responsible Agency’s imposition of additional mitigation more than a year after it had issued an initial approval for the project.  Although the court was careful to say that it was addressing “unique circumstances” that would “seldom arise,” the decision is potentially problematic for project proponents, and especially for public agencies trying to pursue necessary public-infrastructure projects.

In an opinion published on August 17, 2020, the Third Appellate District in Martis Camp Community Association v. County of Placer ruled that Placer County had violated CEQA by adopting an addendum to support abandonment of a roadway. Despite the statutory presumption against subsequent review under CEQA, the Third District determined that the County had

Last month, the Second Appellate District upheld the South Coast Air Quality Management District’s (“Air District”) Environmental Impact Report (“EIR”), which the Air District prepared to analyze the environmental impacts of a refinery project that was intended to increase compliance and help reduce air pollution.  Communities for a Better Environment v. So. Coast Air Quality Mgmt. Dist., Case No. B294732 (Apr. 7, 2020).  The project applicant owns and operates two adjacent oil refining facilities in Southern California, and sought to improve the integration of both facilities to allow flexibility in product outputs, which also increased the refinery’s compliance with air regulations, and thus helped reduce air pollutants.  As explained in greater detail below, the decision is particularly noteworthy because the court appears to have expanded the “baseline” analysis tied to air emissions, which is used to measure pre-project vs. post-project impacts to the existing environment.

The Air District’s review of the underlying project took three years and the Air District’s Draft EIR was the subject of over 2,000 public comments, which included comments totaling 1,112 pages from the plaintiff that later challenged the project.  Significantly, 1,798 comments or 85% supported the project—likely because the EIR found that the main environmental impact of the project would be to reduce air pollution; and the Air District’s Final EIR was lengthy and robust, containing 6,075 pages of public comments alone.