In a split decision in Cleveland National Forest Foundation v. San Diego Association of Governments, 2014 Cal. App. LEXIS 1070, a majority of the three-judge panel of the California Court of Appeal for the Fourth District affirmed a writ of mandate challenging the San Diego Association of Governments’ (SANDAG) environmental review of its 2050
Greenhouse Gas Emissions
Addendum Upheld: Amendments to San Jose Airport Master Plan Cleared For Landing
In Citizens Against Airport Pollution v. City of San Jose (2014) Cal. App. LEXIS 588, the Court of Appeal for the Sixth District upheld the trial court’s denial of a writ of mandate challenging the City of San Jose’s (the City) approval of an addendum to an EIR analyzing the environmental impacts of amendments to…
Trial Court Upholds Approval of Plan Bay Area
On July 2, 2014, Judge Evelio Grillo of the Alameda County Superior Court issued a 30-page decision in Bay Area Citizens v. Assn. of Bay Area Governments, et al (Case No. RG13690631), upholding approval of Plan Bay Area by the Association of Bay Area Governments and Metropolitan Transportation Commission.
Plan Bay Area is the regional…
California Supreme Court Issues Neighbors for Smart Rail Decision: Predicted Conditions Baseline Allowable Under CEQA in Limited Circumstances
In a much anticipated decision, the California Supreme Court held in Neighbors for Smart Rail v. Exposition Metro Line Construction Authority that lead agencies can use future predicted conditions as an environmental baseline in assessing the impacts of proposed projects. The court held that in order for an agency to omit the normally required existing…
Court Turns Tide in Favor of Desalination Plant – Holds Ample Substantial Evidence Supports the Project’s EIR
Almost four years after the Marin Municipal Water District (MMWD) certified an environmental impact report (EIR) and approved a five million gallon a day desalination plant project, the Court of Appeal, First District, in a published opinion (N. Coast Rivers Alliance v. Marin Mun. Water Dist. Bd. of Dirs. (2013) 2013 Cal.App.LEXIS 401), reversed…
Appellate Court Upholds City’s Approval of Large Commercial Project Even with Unknown Impacts on Greenhouse Gas Emissions, Deferred Mitigation, and Rejected Alternative
UPDATE: On August 27, 2012, the Fourth Appellate District Court certified Rialto Citizens for Responsible Growth v. City of Rialto (2012) 2012 Cal. App. LEXIS 849 for full publication.
In a decision certified for partial publication, Rialto Citizens for Responsible Growth v. City of Rialto (2012) 2012 Cal. App. LEXIS 849, the Fourth Appellate District…
Court Holds CARB’s Scoping Plan Complies with AB 32
In Associated of Irritated Residents v. California Air Resources Board, (2012) ___ Cal.App.4th ___, the California Court of Appeal, First District, held that the California Air Resources Board (CARB) complied with the requirements of AB 32, the Global Warming Solutions Act, when it adopted its Climate Change Scoping Plan (Plan).
AB 32 requires, among…
Santa Clarita Organization for Planning the Environment v. City of Santa Clarita (2011) 197 Cal.App.4th 1042
The City of Santa Clarita (City) certified an EIR and adopted a master plan for a project to expand a hospital and medical office space over a 15-year period. The Petitioner challenged the City’s approvals for two reasons: First, the City failed to provide evidence and explanations for why the project’s impact on climate change…
Citizens for Responsible Equitable Environmental Developments v. City of Chula Vista (2011) 197 Cal.App.4th 327
The City of Chula Vista (City) approved a proposed Target retail store in reliance on a mitigated negative declaration (MND). Petitioner filed a petition for writ of mandate challenging the MND and claiming that the project may have significant impacts relating to hazardous materials, air pollution, particulate matter and ozone, and greenhouse gas emissions. The…
Citizens for Responsible Equitable Environmental Development v. City of San Diego (2011) 196 Cal. App. 4th 515
In 1994, the City of San Diego (City) certified an EIR and approved a 665-acre mixed-use development plan. In 2008, the City was approached by a developer who wished to build condominiums on the last remaining open space within that area. The City prepared a water supply assessment (WSA) and an addendum to the 1994…